Butler Plaza and Lawn Restoration - Updates for week of Oct. 16

Miscellaneous work for the Butler Lawn and Plaza restoration project is continuing to be completed. By the end of Wednesday of this week (October 18), new sod is anticipated to be laid down in the southern portion of South Lawn West, which was the location of construction staging during the project. By the end of this week (Oct. 20), installation of the granite and railing for the ramp approaching the library from the north is scheduled for completion. By the end of October, a new entryway to South Lawn West across from Lerner Hall will be completed. Updates on additional work will be shared when scheduled.

Read more for photos and past updates.